Project Details

Square Footage:12,000 plus

Permit Date:9-13-2012

Certificate Of Occupancy Date:10-04-2012

Total Construction Days Start to Finish:22 Calendar Days

Complete Demolition and reconstruction of Tenant Space and common corridors totaling 12,000 S.F. Special request that project be complete within 22 days due to delay in permitting and the fact that the Tenant had already vacated their original location. Complete demolition of all walls and finishes throughout with the exception of the ceiling. Project completed on time to the satisfaction of Thyssen Krupp. All common corridors surrounding space were completely renovated with new wall coverings, new carpeting, ceilings, lighting and new doors.